Print this pageStephens Park Bank Stabilization Project

Stephens Park is a public park located in West Vail in the Intermountain neighborhood.  The park is adjacent to Gore Creek and is also a designated off-leash dog park.  Heavy use of the stream access has resulted in an eroded bank and damage to vegetation.

The Stream Bank Improvement project proposes to install in-stream boulder weirs, bank grading and stone terraces as well as landscaping improvements to the area.

Bid Documents:

Project Manual
with Bid Form, Agreements and General Conditions
Technical Specifications
Drawings

Addendum 1: August 9, 2010

Addendum 1 - Includes updated Bid Descriptions/Bid Form

Drawings (Revised)

Project Manual (Revised) - Bid Form/Descriptions changes, included in Addendum 1

Project Schedule
Plans and Documents available    Monday August 2, 2010
Pre-bid Meeting                          Wednesday, August 4, 2010      10:00 a.m.
Bid Opening                               Tuesday, August 24, 2010         3:30 p.m.  
Presentation to Town Council        Tuesday, September 7, 2010
Notice to Proceed                        Wednesday, September 8, 2010
Commence Site Work                  September 9, 2010
All bank work complete                October 5, 2010
Final Completion                         November 15, 2010 or as weather permits