Stephens Park Bank Stabilization Project
Stephens Park is a public park located in West Vail in the Intermountain neighborhood. The park is adjacent to Gore Creek and is also a designated off-leash dog park. Heavy use of the stream access has resulted in an eroded bank and damage to vegetation.
The Stream Bank Improvement project proposes to install in-stream boulder weirs, bank grading and stone terraces as well as landscaping improvements to the area.
Bid Documents:
Project Manual with Bid Form, Agreements and General Conditions
Technical Specifications
Drawings
Addendum 1: August 9, 2010
Addendum 1 - Includes updated Bid Descriptions/Bid Form
Project Manual (Revised) - Bid Form/Descriptions changes, included in Addendum 1
Project Schedule
Plans and Documents available Monday August 2, 2010
Pre-bid Meeting Wednesday, August 4, 2010 10:00 a.m.
Bid Opening Tuesday, August 24, 2010 3:30 p.m.
Presentation to Town Council Tuesday, September 7, 2010
Notice to Proceed Wednesday, September 8, 2010
Commence Site Work September 9, 2010
All bank work complete October 5, 2010
Final Completion November 15, 2010 or as weather permits